Av Ida Simon-Andersson, HR/Marketing Manager at Nordic Pack AB
You need 300 cans for a test run. The supplier replies that the minimum order is 1,200 and that the lead time is 12 weeks. The problem is rarely in the product. The path to your filling line determines the minimum order quantity in which the packaging is sold, not the material you have chosen.
The minimum order quantity for packaging is determined by the delivery route. If you buy from a warehouse in Sweden, the order can in practice start with a single piece. If the order is direct from the factory, it usually starts with several pallets, as the manufacturer adjusts the machine for your specific item.
Two delivery routes dominate the Swedish packaging market. One goes via a wholesaler who stocks standard assortments in Sweden. The other goes directly from the manufacturer's factory to your facility.
The difference is visible in three numbers: minimum order, lead time and how much capital you tie up before the first unit is sold. A stock order can start with one piece. A factory order starts with a production run, and the run is sized according to the machine — not according to your needs.
The choice of material does not change that logic. Glass, PET and HDPE follow the same pattern, because the pattern is in the economics of manufacturing. How you choose the material, volume and closure is a separate issue, and we have covered that in the guide to plastic bottles for B2B.
Short lead time costs in price per unit. Long lead time costs in flexibility. The choice between them is the single biggest practical difference between the two paths.
Our warehouse in Nykvarn has around 1,000 stocked items, and minimum orders are in practice from one piece upwards. Stock items can usually be shipped within 48 hours, and our ambition is to respond to quotation requests within 24 hours. The short lead time is because someone else has already tied up the capital in the item.
A factory-manufactured order follows the production plan instead of the inventory balance. The manufacturer collects orders for a run, sets up the machine, and produces. The lead time is therefore measured in weeks, not days, and is affected by how many other customers are in the same queue.
The price per unit goes in the opposite direction. The larger the run, the smaller the proportion of changeover cost per unit. That is why a factory rarely says no to a large order and almost always says no to a small one.
Lead time is rarely a single number. It is a chain of steps where each step has its own variation, and the variation is what makes planning difficult.
The warehouse route shortens the chain to two steps: picking and transport. The factory route includes all six. The difference is most noticeable when something goes wrong, because a delay in step three shifts everything behind.
Therefore, plan backwards from the filling date instead of forwards from the order date. A typical case is production that is booked before the packaging is confirmed, and where the entire chain then has to be adjusted for a bottle that is left in a port.
Order size is a cash flow decision before it is a purchasing decision. A calculation example shows the order of magnitude. The numbers below are illustrative and chosen to make the calculation clear — they are not taken from a real customer case.
Assume that a pallet holds 1,200 bottles and that the unit price is 4 kronor. One pallet then corresponds to 4,800 kronor in purchase value. If you fill 150 bottles a month, the pallet will last for 8 months. During those 8 months, 4,800 kronor will sit idle on the shelf, while the item risks being replaced with a new label or a new format.
The same volume divided into 3 deliveries from stock instead ties up around SEK 1,600 at a time. The 2 deliveries you have not yet taken home do not tie up any capital at all. The difference in unit price between the two arrangements is normally a few tens of öre. Calculate both numbers before you decide, since one is visible in the invoice and the other is visible in the cash flow.
Capital tied up is rarely visible in the purchase calculation, as it does not have its own line in the quote. Instead, it shows up as money that is missing when something else needs to be paid. Therefore, calculate the order size in months of consumption in parallel with the unit price, and the cost will be visible before the order is placed.
The unit price is the only figure that appears in the quote. Several of the items that determine the total cost are outside of it.
Shipping and pallet handling are typically added per delivery, making many small deliveries more expensive than a few large ones. Warehousing costs space, and space costs just as much when the pallet is stationary as it does when it is moving. Repackaging costs labor time every time the factory’s package format doesn’t match your line.
Discarding is the item that does the most damage. If you change the label format, volume or closure, the remaining stock becomes difficult to use. A stock that covers eight months of consumption therefore contains eight months of risk due to changed conditions.
Also factor in the cost of capital. Money sitting in a pallet does not finance raw materials, marketing or salaries. For a company with tight liquidity, that item weighs more heavily than a few cents in unit price.
Put all items in the same calculation: unit price, shipping, warehouse space, repackaging, scrap risk and capital cost. Only then will the two delivery routes be comparable. In practice, many buyers find that the cheapest quote is not the cheapest deal.
Large orders lock you into today's conditions. Regulations, customer requirements and your own product portfolio change faster than an eight-month stock can be used up.
The packaging sector clearly demonstrates this. Requirements for labeling, recyclability and reporting have been gradually tightened, and those who have a large stock of an item have fewer options when the requirements change.
Commercial changes work the same way. A new chain customer may require a different format, and a product development may change the fill volume. The longer the inventory lasts, the more of it lies outside the period you can actually overview.
A reasonable rule of thumb is to let the order size follow the period you can forecast with certainty. If you are looking at a quarter, the order should cover a quarter, plus the buffer required by the delivery time.
Direct delivery from the factory often means that you become an importer. The role comes with the product, and it involves administration that does not exist when you buy from a Swedish wholesaler.
Goods imported from countries outside the EU must always be declared with an import declaration, where you state the goods, customs duty and any restrictions (Finnish Customs, 2026). For goods purchased within the EU, in principle no customs declaration is required. (Finnish Customs, 2026)The difference between the two cases is days in customs processing and an entry in your administration.
Producer responsibility follows the same pattern. It covers all businesses that first release packaging on the Swedish market, which includes companies that manufacture or import packaging and businesses that import packaged goods. The EU Packaging Regulation 2025/40 will apply from 12 August 2026 (European Parliament and Council, 2025). From that date, several of the rules that apply in Sweden will change (Swedish Environmental Protection Agency, 2026). Check your own role against the Swedish Environmental Protection Agency's guidance before placing a directive order, as the role determines what you need to report.
The transport distance is the third item. Shorter routes mean fewer transhipments and less exposure to delays, which we have developed in the article about locally produced glass for your packaging.
Call-offs divide a large order into several deliveries. You commit the volume to the supplier, but take the goods home as they are consumed.
The arrangement mitigates the conflict between price and tied-up capital. The factory price assumes a certain run, while your liquidity is better off with small deliveries. With call-off, the volume remains with the supplier until you call it off.
Three things determine whether a call-off contract works: the length of the contract period, who is responsible for inventory, and how much volume you commit to. A 12-month contract with quarterly call-offs requires that you can forecast a year ahead. If the forecast is wrong, you have moved the risk forward in time instead of removing it.
Also ask what applies to the remaining volume if the product is discontinued. An agreement where the entire volume must be taken home is a full pallet order spread out over time, for example with six deliveries instead of one.
Repackaging breaks the connection between the manufacturer's package and your needs. The product arrives in the factory's format, and the warehouse repacks it into the format your production actually uses.
We have staff who work dedicatedly with repackaging in our own warehouse. In practice, this means that a full pallet can be divided into smaller units, or that several items are collected on a common pallet for a campaign. More examples of how we work with this can be found in our customer benefits.
A concrete example: an order for 6,000 bottles comes on five pallets from the factory, while your line needs 500 bottles at a time. The warehouse receives the pallets and repacks them into cartons of 500. Your production gets the right format, and pallet handling takes place where the equipment already exists.
Repackaging solves two recurring problems. The first is production lines that require a certain number of units per carton. The second is the customer's warehouse space, which is rarely dimensioned for the factory's pallet height.
Most B2B buyers need both paths at the same time. The split follows consumption, not supplier.
Items with consistent and high consumption are suitable for direct delivery. The volume bears the changeover cost, and the lead time can be planned because the need is predictable. Items with uneven or uncertain consumption are suitable for stock delivery, for example new formats being introduced and seasonal products.
A common setup looks like this: the main format is ordered directly from the factory twice a year, while test runs, special formats and tops are covered from stock. The buffer stock at the wholesaler then acts as insurance against the long lead time.
The split is rarely even. For most B2B buyers, a few items account for most of the volume, while the rest of the range moves slowly. Put the direct deliveries on the items that carry the volume, and keep the rest in an assortment that you can call in smaller batches.
Test the setup against a simple question. How many months of consumption does the minimum order you are offered correspond to? If the answer is over six months, the capital tied up is likely greater than the price gain.
MOQ stands for minimum order quantity and indicates the smallest order a supplier will accept. The number is expressed either in number of units or in order value. For packaging, MOQ is often set per item number, not per order, which affects how you plan your assortment.
The lead time is calculated in weeks and is controlled by the manufacturer's production plan, not by stock balance. Machine changeover, queue for the run and transport determine the total time. Stock items from a Swedish warehouse can usually be shipped within 48 hours instead.
Yes, but the negotiation costs something else. A lower number normally gives a higher unit price or longer lead time, since the conversion cost is distributed over fewer units. If you choose a standard item instead of a special item, the minimum order usually drops immediately.
The importer brings the product onto the market and thus takes on customs handling and reporting. When importing directly from a country outside the EU, an import declaration is always required, and producer responsibility for the packaging may end up with you. The role determines what you need to register and report.
Minimum order, lead time and capital tied up are three sides of the same decision. The warehouse route gives small orders and short lead times, at the cost of a slightly higher unit price. The factory route gives lower unit price, at the cost of longer lead times, larger minimum orders and more administration.
The decision becomes easier when you calculate in months of consumption instead of in kronor per item. An order that covers eight months is a stock decision, not a purchasing decision.
Are you looking to review your order sizes for next season? Contact us and we will go through the range item by item and calculate what stock delivery and direct delivery mean for your production. Contact us with volumes and formats, and we will return with a basis you can count on.
We use AI as a tool for research and structure. All content is reviewed, fact-checked and rewritten by Ida Simon-Andersson at Nordic Pack AB — who is responsible for every word published.

Now your quotation request is sent to us and one of our sales representatives will process it and get back to you.
Thank you for showing interest in our products!
Questions about packaging solutions? Do you want inspiration and help from our packaging experts? We are happy to answer questions about packaging in general, and we can also offer more products than the ones you see on the website!
Leave your information and write your question in the form. We normally respond within 24 hours.